Below you will see a standard project timescale. However, please note this is an approximation and project timescales can vary. 

Instruction to property survey – 7 days 

Production of full plans and videos for initial scheme after measure – 7 days

Alterations – Clients generally require about 3 weeks to consider and make any alterations, although this varies. We offer a 3-month timescale in which to design schemes and aim to revise plans within 2 days of any request to do so.

Planning (time taken by Local Authority) – 56 days

Production of Building Regulation drawings – 7 days.